|
Clean Water State Revolving Fund Program
GENERAL
INFORMATION
The Clean Water State Revolving
Fund (CWSRF) program was authorized by the U.S. Congress
through Title VI of the Clean Water Act (CWA) as amended in
1987. The Act authorizes the Environmental Protection
Agency (EPA) to provide federal funds to the states to
capitalize State Revolving Funds (SRFs). The SRFs are
established and managed by the states and the states must
provide a 20 percent match for the federal capitalization
grants.
The North Dakota SRF is jointly
managed by the North Dakota Department of Health and the North Dakota Public
Finance Authority. The Department of Health receives the
Federal Capitalization Grant and is responsible for the
technical and overall administrative functions of the
program. The Public Finance Authority, under agreement with
the Department of Health, acts as the Department�s financial
agent and is responsible for the preparation and issuance of
bonds, reviewing the financial capability of political
subdivisions, investing program proceeds, handling loan
repayments, and other necessary financial functions.
Each year, the
Department of Health
prepares a capitalization grant application and submits it
to the Environmental Protection Agency. When the grant
money is received, the Public Finance Authority initiates a
sale of bonds to be used for the state�s 20 percent match
requirement. The capitalization grant and bond proceeds are
deposited in the SRF and made available to political
subdivisions for eligible projects. As communities pay back
their loans, the interest payments are used to retire the
state match bonds and the principal is deposited in the SRF
to be used for additional projects. The revolving aspect of
the program will assure that North Dakota has funds for needed
projects far into the future. The current rate for SRF
loans is 2.5 percent plus a .5 percent administration fee
for a maximum term of 20 years.
FEDERAL REQUIREMENTS
SRFs have replaced the old
Construction Grants Program as the major funding source for
upgrading community wastewater systems. Under the SRF,
however, project eligibilities have been expanded and federal requirements reduced. The following types of
projects are eligible for SRF funding:
Even though certain
federal
requirements have been eliminated in the SRF Program, there
are still a number of them that must be complied with.
These fall within two categories, equivalency requirements
and �cross-cutting� requirements. The equivalency category
consists of those requirements that were carried over from
the Construction Grants Program and apply mostly to the
technical and engineering aspects of the SRF program.
Equivalency
requirements do not apply to nonpoint source projects.
The �cross-cutting� requirements
may be contained in other federal laws, Executive Orders or
government-wide policy statements and generally apply
broadly to a wide range of federal financial assistance
programs. These cross-cutting federal authorities can be
divided into three groups. First, several environmental
laws and executive orders relating to such things as
preservation of historical and archaeological objects,
endangered species, wetlands, agricultural land and the
like, apply to construction activities. Second, are
requirements such as minority and women�s business
enterprise participation goals and equal employment
opportunity rules that can be classified as social
authorities. Third, are cross-cutting authorities, such as
the prohibition against entering into contracts with
debarred or suspended firms, that directly regulate the
expenditure of federal funds. A complete listing of
authorities is attached.
LOAN APPLICATION PROCESS
Before a political subdivision
can receive loan money, their proposed project must be
identified on the Project Priority List and the Intended Use
Plan. These are documents required by federal regulation
and prepared by the Department of Health annually. To be
included on the lists, a community should notify the
Department of Health of their intent as soon as possible. While an
application can be processed and preliminary work completed
without being on these lists, no funds can be transferred to
the community until their project appears on the approved
documents.
Application packets can be obtained from
either the Department of Health, the Public Finance Authority,
or online at http://www.nd.gov/pfa/srf.html.
|
North Dakota
Department of Health
Division of Municipal Facilities
918 East Divide Avenue, 3rd Floor
Bismarck, ND 58501-1947
701.328.5211 Fax 328.5200 |
North Dakota Public
Finance Authority
1200 Memorial Highway
P.O. Box 5509
Bismarck, ND 58506-5509
701.328.7100 Fax 328.7130 |
When the Department is contacted regarding
an application, depending on the complexity of the project,
a preapplication meeting may be scheduled. At this meeting,
a representative of the Department will explain the program,
answer any question and assist the community as needed.
Upon completion, copies of the application should be sent to
both the Department of Health and the Public Finance
Authority. The Department of Health reviews the technical and
programmatic aspects and the Public Finance Authority
reviews the financial information. If additional
information is needed, the community will be promptly
notified.
PROFESSIONAL
SERVICES
A community will typically
require the services of a consulting engineer and bond
counsel. The engineer is responsible for preparing all
required technical documents. These include the facility
plan, building plans, specifications, bidding documents,
operation and maintenance manuals, and others. In addition,
the engineer provides on site inspection services during
construction to insure quality control and construction in
accordance with the approved plans and specifications. The
Department of Health will work closely with the community�s
engineer to assure compliance with federal and state
requirements. The Public Finance Authority will work with
the community�s bond counsel to assure that all legal and
financial requirements are met.
PROJECT
DEVELOPMENT
The typical SRF project consists
of three steps, the facility plan, plans and specifications,
and construction. As the name implies, the facility plan is
a planning document that establishes existing conditions,
identifies the current problems, projects future conditions
at the design year, and evaluates alternatives to solve the
existing problems and meet future needs. The evaluation of
alternatives includes both a cost effectiveness analysis and
an environmental assessment. The intent of the facility
plan is to arrive at the most cost effective,
environmentally sound solution to the problem. The facility
plan must be approved by the Department of Health before the
project can proceed to the next step.
When the facility plan is approved, plans, specifications,
and bidding documents are prepared based on the recommended
alternative from the facility plan. These must comply with,
among other things, MBE/WBE and EEO requirements. Once the
documents are approved by the Department of Health, the project
can be advertised and bids opened. If the bids are
acceptable, the construction contract must be awarded to the
low, responsive, responsible bidder following Department of
Health approval. Construction can now begin at the
community�s convenience.
At this time, the Department
of Health will schedule a preconstruction meeting with the
community and contractor to explain the construction related
requirements that must be complied with and to answer any
questions that arise. In addition to the preconstruction
meeting, periodic interim inspections will be conducted by
Department of Health engineers during the construction phase of
the project. Since SRF loans are cost reimbursable,
construction costs must be incurred before the community can
receive payments. Once costs are incurred, the community
should submit periodic payment requests to the Department of
Health for processing. Payment should be received by
the community within two weeks of receipt of the request by
the Department. When construction is completed, the Department
of Health will conduct a final inspection to verify
compliance with federal requirements, verify that the
project was constructed in accordance with the approved
plans and specifications, and establish final costs.
Repayment of principle must
begin no more than one year after the project is declared
operational. Prior to this, the Public Finance Authority
will work with the community to establish a repayment
schedule.
EQUIVALENCY REQUIREMENTS OF
THE SRF PROGRAM
Title VI of the Clean Water Act lists 16 specific Title II
requirements which must be met for section 212 projects funded in an
amount equal to the capitalization grants. These 16 are 201(b),
201(g)(1), 201(g)(2), 201(g)(3), 201(g)(5), 201(g)(6), 201(n)(1),
201(o), 204(a)(1), 204(a)(2), 204(b)(1), 204(d)(2), 211, 218, 511(c)(1),
and 513.
-
Section 201(b)- Requires that projects apply best
practicable waste treatment technology.
-
Section 201(g)(1)- Limits assistance to projects
for secondary treatment, advanced treatment, or any cost-effective
alternative, new interceptors and appurtenances, and
infiltration-inflow correction. Allows up to 20 percent of the
yearly allotment for other projects within the definition of
treatment works in section 212(2).
-
Section 201(g)(2)- Requires that alternative
technologies be considered in project design.
-
Section 201(g)(3)- Requires the applicant to show
that the related sewer collection system is not subject to excessive
infiltration.
-
Section 201(g)(5)- Requires that applicants study
innovative and alternative treatment technologies and take into
account opportunities to construct revenue producing facilities and
to make more efficient uses of energy and resources.
-
Section 201(g)(6)- Requires that the applicant
analyze the potential recreation and open space opportunities in the
planning of the proposed facility.
-
Section 201(n)(1)- Provides that funds under
section 205 may be used for water quality problems due to discharges
of combined sewer overflows, which are not otherwise eligible, if
such discharges are a major priority in a state.
-
Section 201(o)- Calls on the
state to encourage
and assist communities in the development of capital financing plans
-
Section 204(a)(1) and (2)- Requires that treatment
works projects be included in plans developed under section 208 and
303(e).
-
Section 204(b)(1)- Requires communities to develop
user charge systems and to have the legal, institutional,
managerial, and financial capability to construct, operate, and
maintain the treatment works.
-
Section 204(d)(2)- Requires that, one year after
the date of completion of construction and initiation of operation
the owner/operator of the treatment works must certify that the
facility meets design specifications and effluent limitations
included in its permit.
-
Section 211- Provides that major rehabilitation or
replacement of collectors is not eligible under the Governor's 20
percent discretionary authority, unless the collector is needed to
assure the total integrity of the treatment works or that, for a new
collector, adequate capacity exists at the treatment facility.
-
Section 218- Assures that treatment systems are
cost-effective and requires that projects of over $10 million
include a value-engineering review.
-
Section 511(c)(1)- Applies the Environmental
Impact Statement requirement of the National Environmental Policy
Act to treatment projects.
-
Section 513- Applies Davis-Bacon labor wage
provisions to treatment works construction.
CROSS CUTTING AUTHORITIES
ENVIRONMENTAL
-
Archeological and Historic Preservation Act
-
Clean Air Act
-
Endangered Species Act
-
Executive Order 11593- Protection and Enhancement of the
Cultural Environment
-
Executive Order 11988- Floodplain Management
-
Executive Order 11990- Protection of Wetlands
-
Farmland Protection Policy Act
-
Fish and Wildlife Coordination Act
-
National Historic Preservation Act
-
Safe Drinking Water Act
-
Wild and Scenic Rivers Act
ECONOMIC
-
Demonstration Cities and Metropolitan Development Act
-
Section 306 of the Clean Air Act and Section 508 of the Clean
Water Act, including Executive Order 11738-Administration of the
Clean Air Act and the Federal Water Pollution Control Act with
Respect to Federal Contracts, Grants, or Loans
SOCIAL
-
Age Discrimination Act
-
Civil Rights Act of 1964
-
Executive Order 11246- Equal Employment Opportunity
-
Executive Orders 11625 and 12138- Women's and Minority Business
Enterprises
-
Section 13 of PL 92-500; Prohibition against sex discrimination
under the Federal Water Pollution Control Act
MISCELLANEOUS AUTHORITY
|
|